Glossary entry (derived from question below)
French term or phrase:
avance de demarrage
English translation:
advance for preliminaries/mobilization costs
Added to glossary by
dholmes (X)
Jun 8, 2007 08:06
17 yrs ago
18 viewers *
French term
avance de demarrage
French to English
Tech/Engineering
Construction / Civil Engineering
technical project study
"Après avoir retenu l'Entreprise, le client peut tarder à donner l'ordre de service de démarrer les travaux ou une avance de démarrage."
"Travaux" is construction of bridges, tunnels buildings etc.
"Travaux" is construction of bridges, tunnels buildings etc.
Proposed translations
(English)
4 | advance for preliminaries/mobilization costs | Bourth (X) |
2 | a starting advance payment / downpayment | BusterK |
Proposed translations
1 day 15 hrs
Selected
advance for preliminaries/mobilization costs
"preliminaries" being UK, "mobilization costs" US.
Scott/Penguin Dict. of Bldg
le client peut tarder à donner :
i) l'ordre de service de démarrer les travaux
ou
ii) une avance de démarrage
Under the terms of the contract, the contractor may be entitled to refuse to actually start work or put himself in a position to start work if no advance payment for establishing that "readiness" position has been paid, even if the order to commence has been given.
Scott/Penguin Dict. of Bldg
le client peut tarder à donner :
i) l'ordre de service de démarrer les travaux
ou
ii) une avance de démarrage
Under the terms of the contract, the contractor may be entitled to refuse to actually start work or put himself in a position to start work if no advance payment for establishing that "readiness" position has been paid, even if the order to commence has been given.
4 KudoZ points awarded for this answer.
Comment: "Thank you"
19 mins
a starting advance payment / downpayment
not sure to put in exactly the right words but the fact is that it is a matter of payment.
Peer comment(s):
neutral |
Emma Paulay
: Are you sure? Couldn't it possibly be a decision to begin earlier?//It's worded rather clumsily but it might mean "the company can either postpone or bring forward the start date.." No?
46 mins
|
delaying a decision to begin earlier would be quite strange... In addition, when the enterprise is selected, it requires an advance payment and the two way to postpone are then 1° delay the service order and then 2° delay the advance payment.
|
Something went wrong...